Work completed/in progress:

  • Structure was filled with water for the leak test.
  • Sand continues to be stockpiled on the site for future backfilling of the lift station structure.
  • The structure successfully passed its leak test and will be drained of water.

Anticipated work activities for the coming week:

  • Grand River will apply a waterproofing coating to the exterior of the structure.
  • Preparations will begin for installing the bridge crane in the station.