Tree removal is now complete and the real work can begin. Water main installation will begin on Butler Street in the early week. Work on Catherine will consist of pavement removal, concrete removals and preparations for sanitary sewer replacement.
Work Completed This Week
- Trees were removed on Catherine and Butler in preparation of utility work.
Anticipated Work – Butler
- Water main installation will take place in the early week.
- Testing of the new water main will start near the end of the week.
Anticipated Work – Catherine
- The road surface is scheduled for removal on Tuesday March 3. Temporary gravel access to residents will be maintained.
- Concrete curb and drives will be removed Wednesday, March 4 through Friday, March 6.
- Preparation for utility work will be ongoing throughout the week.