Total pipe installed ~16,800 ft of 64,000 ft = ~26%
Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
K&R crossed Whitetail Ct with pipeline this week.
Approximately 4,000′ of pipe has been installed on this project.
K&R continues to lay pipe in Van Buren progressing east from 160th. They are approximately 400′ west of Whitetail Ct.
Van Buren Street from US-31 to 120th Avenue is closed.
K&R crossed 128th Avenue with pipeline this week and is restoring the intersection.
Approximately 3,800′ of pipe has been installed on this project.
Next week, K&R will continue to lay pipe in Van Buren progressing east. A small section of pipe just east of 128th Avenue will be skipped until additional materials arrive. This section of pipe will be installed later.
New Holland Street from 104th Avenue to 96th Avenue is closed.
Ric-Man continued pipe installation in New Holland Street. Approximately 900′ of pipe in New Holland Street remains to be installed.