Work completed/in progress:
- Installed pipe through casing beneath 68th Avenue.
- Installing restraint collar and air release structure west of 68th Avenue.
- Preparing pipe for pressure test.
Anticipated work activities for the coming week:
- Dig up and replace poor joint near 64th Avenue.
- Perform pressure test once joint is replaced.
- Continue fusing lengths of HDPE pipeline.