Work completed/in progress:
- The lower portion of the structure has been dampproofed and backfilled.
- Supports and runway beams for the bridge crane have been installed.
Anticipated work activities for the coming week:
- The next section of the structure will be dampproofed and backfilled.
- The bridge crane will be installed.
- Grand River will place shoring in the wet well in preparation for the wet well lid pour.