Work completed/in progress:

  • The lower portion of the structure has been dampproofed and backfilled.
  • Supports and runway beams for the bridge crane have been installed.

Anticipated work activities for the coming week:

  • The next section of the structure will be dampproofed and backfilled.
  • The bridge crane will be installed.
  • Grand River will place shoring in the wet well in preparation for the wet well lid pour.