There will be a public meeting regarding this project on Monday, March 3 at 6pm at Buchanan City Hall.
Contractor plans on pulverizing asphalt roads throughout the project starting Tuesday March 4th. This will involve grinding down the asphalt roads and turning them to gravel (compacted millings). Roads will remain open to local traffic during this process with only single lane closures needed as work progresses. See attached “mill limits” map for locations. Roads will remain open to local traffic with single lane closures as needed. Red Bud will be closed to through traffic and will need to use the detour route.
Underground pipe work (water main) will begin on Wednesday (March 5th). Red Bud will be closed to all traffic from 3rd Street to Front Street. Also Dewey Street East of Red Bud will be closed. Access to Clark building will be possible from 3rd Street. See attached “Road closure” map. This area will remain closed for the foreseeable future.