Work completed/in progress:
- Grand River stripped forms from the lift station walls and began tying steel for the concrete wet well fillets.
Anticipated work activities for the coming week:
- The first set of wet well fillets will be poured.
- Grand River will begin forming and installing conduit for the intermediate dry well platform.