Site work has begun on the new pedestrian tunnel crossing under M-52 (South Main Street) in the City of Adrian.  Work began this past Monday.  Construction is scheduled to be completed before Labor Day 2026. Lane closures may begin later next month, in mid to late February, on M-52. We will keep everyone as informed as possible with these weekly updates.

Progress Report

Upcoming Work Planned for Next Week:

Recent construction photos from the site courtesy of Mannik Smith Group:

Crews are installing dewatering wells on the west side after tree stump removal.

 

Crews are installing dewatering wells on the east side of M-52.