Work completed/in progress:

  • Laid approximately 900′ of force main along Railroad corridor on north side of Continental property.
  • Pulled force main through casing beneath Railroad spur.

Anticipated work activities for the coming week:

  • Continue force main installation along Railroad corridor on north side of Continental property. Install adjacent to electrical substation and continue to 68th Avenue.
  • No work planned for Monday or Tuesday due to cold weather.