Work completed/in progress:
- No work Mon-Wed due to the winter storm.
- Plowed work area after winter storm.
- Continued force main installation along Railroad corridor on north side of Continental property, including pulling the force main through the casing installed adjacent to the electrical substation.
Anticipated work activities for the coming week:
- Continue force main installation along Railroad corridor on north side of Continental property progressing toward 68th Avenue.