Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
This week, K&R performed joint work within the pipeline. Next week, K&R will start dewatering between 160th and 152nd Avenue in preparation for pipe laying the week of 1/19, otherwise there will not a lot of activity on-site.
Van Buren Street from US-31 to 128th Avenue is closed.
K&R resumed pipe laying this week, progressing west to east. Next week, there will not be a lot of activity on-site. Pipe laying will resume the week of 1/19.
Van Buren Street from 104th Avenue to 96th Avenue has been reopened.
New Holland Street from 104th Avenue to 96th Avenue is closed.
Ric-Man has begun removal and replacement of transmission main in New Holland Street, progressing west to east. Work is expected to continue for several weeks.
Excavation for the surge tank building foundation is anticipated to resume next week.