FRIDAY, JANUARY 9, 2026

  • Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
  • This week, K&R performed joint work within the pipeline. Next week, K&R will start dewatering between 160th and 152nd Avenue in preparation for pipe laying the week of 1/19, otherwise there will not a lot of activity on-site.

 

  • Van Buren Street from US-31 to 128th Avenue is closed.
  • K&R resumed pipe laying this week, progressing west to east. Next week, there will not be a lot of activity on-site. Pipe laying will resume the week of 1/19.

 

  • Van Buren Street from 104th Avenue to 96th Avenue has been reopened.
  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man has begun removal and replacement of transmission main in New Holland Street, progressing west to east. Work is expected to continue for several weeks.

 

  • Excavation for the surge tank building foundation is anticipated to resume next week.
Contact a Location
Learn About Us
View Our Services
Facebook-f Linkedin Youtube Instagram

© 2026 Prein&Newhof, All Rights Reserved

  • Plan Room
  • Lab Results
  • Construction Updates
  • Survey Request