Progress Report:

Kentwood Excavating has made good progress installing new water main along Hillsdale Avenue. A new leaching basin and storm sewer has also been installed at the intersection of Hillsdale and Providence to replace the structure that was removed for water main construction. Kentwood Excavating was only on site Monday this week as they are waiting for Consumers Energy to relocate two (2) utility poles on Hillsdale.

Upcoming Work:

Kentwood Excavating plans to be back on site starting next week (7/13). If the utility poles have not yet been relocated, Kentwood Excavating plans to start water main construction on Lindburg.