Link to presentation slides from July 29 meeting: 164th Ave Open House Presentation
- Van Buren Street from Butternut to US-31 is closed.
- The intersection of Van Buren Street and 136th Avenue is closed and is scheduled to be paved and reopened today. Some driveway paving may be completed.
- 144th Avenue, south of Van Buren, is scheduled to be closed starting this afternoon in preparation for pipeline installation. Closure is expected to last 2-3 weeks.
- Restoration work continued between 160th and 152nd. Road reconstruction between 144th Avenue and 136th Avenue will begin soon.
- Various pipe, structure, and culvert installation occurred this week within the closure area.
- Next week pipe laying will resume at the 144th Avenue crossing and east of 136th Avenue.
- Work inside the pipe continues.
- On August 29, the city held an informational meeting for residents along 164th Avenue. 164th Avenue is scheduled to close the week of August 10. Next week, K&R may begin some exploratory work along 164th Avenue in preparation for pipe laying.
- Van Buren Street from US-31 to 120th Avenue is closed.
- Preparations will continue next week for the tunneling beneath US-31 and the Railroad.
- Pipe laying is expected to resume mid-August.
- New Holland Street from 104th Avenue to 96th Avenue is closed.
- Work continued on restoration within New Holland Street.
- Work in New Holland Street will continue next week in preparation for paving.