Progress Report:

Water main tie-ins were completed at the intersections of Westwood and Ambrose and Hillsdale and Eldon earlier this week. Kentwood worked on short side water service replacements on the west side of Hillsdale most of this week.

Upcoming Work:

Kentwood has a subcontractor coming in next week to begin fusing bypass piping for the temporary water main along Westwood Drive. They will also begin installing new water services under the road on Hillsdale to replace water services to homes on the east side. This work will be done without impacting the road. Water service replacements on Lindburg are also scheduled for next week.