Dean’s continues to progress east with the new 21-inch PVC sanitary sewer. Dean’s had Diversified Dewatering install a groundwater dewatering system end of this week. The existing soils have changed to mostly sand which allows for easier groundwater dewatering. Prior to this week the existing soils were primarily clay at the bottom of the trench which do not allow for a traditional dewatering system to be installed. The dewatering system should help speed up the installation of the pipe up toward Egypt Valley.

Sewer installation will continue next week towards Egypt Valley.