Progress Report

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue

Upcoming Work Planned for Next Few Weeks:

FIVE Lead Goosenecks on ONE service line on Peck Street! All removed and replaced with copper

 

Crews installing a 14-inch insertion valve on Hackley at Baker Street

 

Crews backfilling over top new water main in Maplewood Avenue between Jefferson and Sanford