You have likely seen various activities on site over the last week. Miss Dig flags have been placed and are marking existing underground utilities, construction staking is underway, and driveway/road removals have been marked out.
Kentwood Excavating plans to have a crew on site starting next week to begin water main construction along Hillsdale Avenue. Construction will begin at the Hillsdale and Eldon intersection and progress south.