Van Buren Street from Butternut to 136th Avenue is closed.
The intersection of 160th and Van Buren was reopened on June 13.
Road building between 160th and 152nd has begun. During road building, K&R will be performing spot excavations to seal off various pipeline appurtenances. Paving for this length of road is tentatively scheduled for the week of July 6.
Pipe laying between 152nd and 144th Avenue restarted approximately 500′ east of 152nd Avenue and is continuing eastward.
Pipe laying between 144th and 136th Avenue has progressed east of 140th Avenue and will continue eastward next week.
Van Buren Street from US-31 to 120th Avenue is closed.
Road building continues between US-31 and 128th Avenue.
Pipe laying is expected to resume near the end of July.
New Holland Street from 104th Avenue to 96th Avenue is closed.
Work continued on various pipe appurtenances within New Holland Street.
Excavation for placement of the valve and valve vault north of New Holland Street began.
Valve vault and valve are expected to be installed next week. This is the last length of transmission main to be installed on Contract 3.