  • Van Buren Street from Butternut to 136th Avenue is closed.
  • The intersection of 160th and Van Buren was reopened on June 13.
  • Road building between 160th and 152nd has begun. During road building, K&R will be performing spot excavations to seal off various pipeline appurtenances. Paving for this length of road is tentatively scheduled for the week of July 6.
  • Pipe laying between 152nd and 144th Avenue restarted approximately 500′ east of 152nd Avenue and is continuing eastward.
  • Pipe laying between 144th and 136th Avenue has progressed east of 140th Avenue and will continue eastward next week.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • Road building continues between US-31 and 128th Avenue.
  • Pipe laying is expected to resume near the end of July.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Work continued on various pipe appurtenances within New Holland Street.
  • Excavation for placement of the valve and valve vault north of New Holland Street began.
  • Valve vault and valve are expected to be installed next week. This is the last length of transmission main to be installed on Contract 3.
Contact a Location
Learn About Us
View Our Services
Facebook-f Linkedin Youtube Instagram

© 2026 Prein&Newhof, All Rights Reserved

  • Plan Room
  • Lab Results
  • Construction Updates
  • Survey Request