Progress Report

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue

Upcoming Work Planned for Next Few Weeks:

 

New 18-inch transmission main valve installed in Norton Avenue near Peck Street:

Broadway: Gravel road base is installed and some sidewalks have been installed. Looking west at 6th Street:

Broadway: Gravel road base is installed and some sidewalks have been installed. Looking east at 6th Street:

Old storm drain pipe removed in Maplewood between Sanford and Jefferson:

New storm drain pipe ready for installation after the water main is installed in Sanford, north of Maplewood: