Schirmer Opening? It was supposed to be open last week, but guard rail got delayed. New opening date will be posted as soon as possible.
Work Completed this past week (June 16-20)
- C1, Sanitary sewer installed on Red Bud from Dewey to McCoy Creek.
- C1, completed storm sewer on 3rd Street up to McCoy Creek.
- C3, Water main pipe installation completed on Front Street, Days Ave to Oak Street.
- C3, water main testing completed and ready for services on Front Street between Red Bud and Days Ave.
- C3, pavement removals completed on Front Street at Oak Street intersection.
- Front/Oak Street intersection closed on Thur (6/19) for water main install.
- Paved Liberty Street/Rynearson Street Saturday (6/14).
Work planned for this week (June 23-28)
- C1, continue sanitary sewer install on Red Bud between Dewey and Front, crossing McCoy Creek early next week.
- C1, anticipated road building on 3rd Street to start June 30th.
- C3, finish installing water main pipe at Front/Oak Street intersection.
- C3, begin water main/water service connections on Front between Days and Red Bud (pending C1 sanitary sewer progress).