Progress Report
- Pavement removal continued west of 5th Street and began at Temple, heading west to Glade Street
- Preparations were made for the water main installation to begin on Broadway Avenue next week
- Water main repairs were made to the system at Hoyt Street between Maplewood and Seaway
The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.
Upcoming Work Planned for Next Few Weeks:
- Tree removals will begin on Sanford Street south of Oakwood and at Delano and Riordan
- Full-depth pavement removal will continue in the middle and north portion of Broadway Avenue
- Water main installation will begin on Broadway Avenue at Temple Street, and work west
- Water main installation will begin on Broadway Avenue at 5th Street, and work west