Work completed/in progress:
- Hydrostatic pressure test for first segment of pipe passed.
- 600′ of pipe installed along Railroad corridor west of 68th Avenue
- Continued fusing lengths of HDPE pipeline.
Anticipated work activities for the coming week:
- Continue fusing lengths of HDPE pipeline.
- Resume pipe laying west of 68th Avenue along the Railroad corridor.