Work completed/in progress:

  • Wet well lid was poured.
  • Backfill continued.
  • Grand River began constructing forms for dry well lid.

Anticipated work activities for the coming week:

  • Installation of steel, conduit, and floor drains in dry well lid, which is currently scheduled to be poured the week of March 24.
  • Installation of underground structures and gravity sewer.