Work Completed this past week (March 10-15)
- Contractor completed pulverizing 3rd Street and Dewey, as well as milling the road on Red Bud and Main Street.
- H piles installed on the North side of the creek off 3rd Street. Holding off on the South side H piles until after pH area excavation complete.
- Direction drilling of water main pipe started on Dewey Street.
- Sidewalk and curb removals started on Red Bud. Access to businesses still possible.
- Water main install started on Red Bud and Dewey Street.
- High pH area excavation completed just East of Fitness Center.
- Concrete infill at Wastewater Treatment Plant.
- AEP was on site review conflict issues of poles.
Work planned for this week (March 17-21)
- Contractor planning on doing directional drill of pilot water main pipe on Red Bud Saturday (3/15)
- Direction drill installation of water main on Red Bud.
- Construction on Liberty Street between Front and Rynearson will begin Monday (3/17) to remove pavement/gravel and place new gravel. Residents notified. Liberty planned to reopen to traffic on Thursday (3/20).
- Grout flume at WWTP.
- H pile install on the South side of the creek on 3rd Street.
- Aerial steel work installing saddles on the creek cross will occur.
- Continue water main install on Dewey (West of Red Bud) and Main Street (Front to Dewey)
- Northbound Main Street will close to traffic around mid-week.
- Reinstall watermain in the area along 3rd street that was removed for excavation of the pH area material.
- Start testing of installed water main.
- Bypass sanitary sewer at Wastewater Treatment Plant and tie in the Flume.
- K&R will not be working on Friday 3/21 (in-house company-wide safety training).
- Two light poles on Red Bud will be removed.