B&Z is starting to hit their stride. They continue to conduct verifications on Monday and Friday, and generally work on replacements on Tuesday, Wednesday, and Thursday. Below is a summary of weeks 1 and 2:
Coming up next, B&Z plans to continue to move northward staying west of Lowe Street within the project area.
Last, below is a snip from our tracking system.