Work completed/in progress:

  • The Diversion Chamber was placed, and 48-inch sewer installation began.
  • Base mat of steel was installed in the dry well lid, and floor sleeves and conduit were added.

Anticipated work activities for the coming week:

  • Remaining conduit and steel will be installed in the dry well. The dry well lid is scheduled to be poured late next week.
  • Installation of underground structures and sewer will continue.