Van Buren Street from Butternut to 160thAvenue is closed, from 160th to 152nd Avenue is closed, and from 152nd to 144th is closed.
K&R spent most of this week preparing the area between Butternut and 160th Avenue for road building. Work included general site cleanup and miscellaneous external and internal pipe work.
Road building between Butternut and 160th Avenue is anticipated to begin shortly.
Next week, K&R may continue pipe laying through Quail Meadow Court, weather permitting.
Van Buren Street from US-31 to 120thAvenue is closed.
Pipe deliveries for work east of US-31 are complete.
Pipe laying is approaching 124th K&R plans to cross 124th Avenue this coming week, weather permitting.
Work inside the pipe continues.
New Holland Street from 104thAvenue to 96th Avenue is closed. The road is closed with an open trench across the street for pipe installation. The trench will be backfilled and the road open by end of Monday, 3/30.
Ric-Man is working on connections from the New Holland Street pipe to the easement piping previously installed. They installed one gate valve north of New Holland Street this week and are working on installation of a second gate valve south of New Holland Street.
One of two 42″ ball valves arrived on site this week.
Next week, Ric-Man will continue working on piping in this area, including installation of a valve vault south of New Holland Street.