Work Completed this past week (March 24-28)
- Work on aerial crossing progressed. Welders onsite.
- Removals on Red Bud North of 3rd Street (center line to East curb/sidewalk only)
- Water main install complete on Dewey and Red Bud, testing pending.
- Two street light poles on Red Bud removed
- Sanitary sewer bypass at WWTP complete, new flume in operation for 15-inch sewer. Ex. 18-inch sewer still using old flume.
- Continued installing sanitary sewer up to SNE2.
- Added manhole over the 24-inch and tie in the 12-inch Ex. by WWTP
- Installing carrier bracket and saddle of aerial crossing (welding in process)
Work planned for this week (March 31-April 4)
- Four Insert-a-valves to be installed (3/31-4/1)
- Install Carrier Casing for aerial crossing.
- Continue water main install on Main Street (Front to Dewey) and on 3rd Street (Red Bud to Short)
- Testing of water main in the area along 3rd street that was removed for excavation of the pH area material.
- Water main shut down on 3rd Street (Red Bud to Skyline) for reconnection. Date of shut down unknown pending testing/sampling.
- Continue sanitary sewer install from SNE2 and cross creek to 3rd Street.