FRIDAY, MARCH 6, 2026

  • Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
  • K&R crossed Martini Ln with pipeline this week.
  • K&R continues to lay pipe in Van Buren progressing east from 160th. They are approximately 600′ west of Buck Fever Drive.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • K&R continued laying pipe east of 128th Avenue. Next week, they will continue to lay pipe.
  • K&R has pipe staged to nearly 104th Avenue and will continue staging pipe along the remainder of the route.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man continued pipe installation in New Holland Street. They will complete initial pipe installation in New Holland Street next week.
  • Next week, Ric-Man will begin making connections from the New Holland Street pipe to the easement piping previously installed. Connections will include installation of precast vaults, valving, and piping.
Contact a Location
Learn About Us
View Our Services
Facebook-f Linkedin Youtube Instagram

© 2026 Prein&Newhof, All Rights Reserved

  • Plan Room
  • Lab Results
  • Construction Updates
  • Survey Request