Work completed/in progress:

  • Dampproofing and backfill of the lift station structure continued.
  • The bridge crane was installed.
  • Grand River installed formwork and steel for the wet well lid.

Anticipated work activities for the coming week:

  • Structure backfill will be completed.
  • The wet well lid will be poured.
  • Grand River will begin installing forms, steel, and conduit for the dry well lid.