Work completed/in progress:
- Dampproofing and backfill of the lift station structure continued.
- The bridge crane was installed.
- Grand River installed formwork and steel for the wet well lid.
Anticipated work activities for the coming week:
- Structure backfill will be completed.
- The wet well lid will be poured.
- Grand River will begin installing forms, steel, and conduit for the dry well lid.