FRIDAY, MAY 1, 2026

  • Coopersville continues to drain its emergency storage ponds in preparation for biosolids removal and WWTP decommissioning.
  • Tree clearing has continued, and I-96 shoulder closure preparations have begun. The Contractor is anticipated to mobilize May 11, with the fusing and HDD subcontractor arriving on site May 18.