Van Buren Street from Butternut to 160thAvenue is closed, from 160th to 152nd Avenue is closed, and from 152nd to 144th is closed.
The intersection of 160th and Van Buren was closed this week and will remain closed for approximately two weeks for pipe installation and culvert replacement within the intersection.
Road building and restoration efforts continued between Butternut and 160th The road is taking shape and gravel has been placed. Asphalt paving is planned for the week of May 11.
Next week, Van Buren Street from 144th to 136th will be closed. K&R will begin road removal, mailbox relocation, pipe staging, etc. in preparation for pipe laying. Pipe laying is expected to start the week of May 17.
Van Buren Street from US-31 to 120thAvenue is closed.
Pipe laying continues eastward. Pipe laying will continue next week as well as work inside the pipe. Later in the week, the crew will be falling back to install various appurtenances on pipe already installed.
New Holland Street from 104thAvenue to 96th Avenue is closed.
Ric-Man completed connections to the existing 54″ transmission main and began filling the drained portion of the 54″ transmission main last night.
Next, Ric-Man and Wyoming will commence flushing, disinfection, and testing required to return the 54″ transmission main to service.
At the Drinking Water Plant, progress has been made over the last few weeks preparing the excavation for construction of the lower level of the surge tank building. Progress will continue next week with dewatering.