Here is another weekly update on the recent work performed in Muskegon Heights on water main and road improvements.

Progress Report

The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.

The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street

Upcoming Work Planned for Next Few Weeks:

 

Crews installing a new sanitary sewer manhole at Broadway and 7th

 

Crews protecting existing utilities in the intersection of Broadway and 7th

 

Crews installing a new fire hydrant on Delano