Work Completed this past week (May 12-17)
- Continued sanitary sewer install, crossed McCoy Creek at 3rd Street.
- Installed large storm sewer treatment unit at City Hall parking lot.
- Traffic to Red Bud Fitness switch to Skyline Drive. This will remain the route for traffic here until Red Bud is complete.
- Water main reconnection on 3rd Street in front of Red Bud Fitness and Dewey/Main St-North planned for Saturday morning (5/17).
- Front Street Closed (Eastbound lane only) between Liberty and Rynearson for Retaining Wall repair (not part of Infrastructure project).
Work planned for this week (May 19-23)
- Continue sanitary sewer install on 3rd Street/City Hall parking lot.
- Work to begin on Front Street Tuesday, May 27.