Pocket Park between Catchmark and Bell’s Furniture:
  • Seatwalls have been poured
  • Concrete curb and gutter has been completed
Goodrich Park Parking Lot:
  • Curb and sidewalk has been poured
  • Area graded and gravel placed
  • Conduit placed for new lighting
Spring Street Parking Lot:
  • New curb has been poured
  • New storm catch basins placed
  • Preparations for new lighting with new conduit
  • Preparations for grading for new pavement
Shared Parking Lot east of Mears:
  • New curb and sidewalk has been placed
  • Preparations for grading for new pavement
  • ***NOTE: We will also now be resurfacing the alley south to Spring Street with this project***
 Goodrich Park Fishing Pier:
  • Pilings installed
  • New boulders (rip-rap) installed under the new decking
  • New deck is being installed
Work expected the week of May 20, 2024:
  • Waiting for old lights to be removed from Goodrich Park and Spring Street Parking Lots
  • Pouring new concrete ramp and stairs to the Fishing Pier
  • Finish the new deck at the Fishing Pier and Railings
Work expected the week of May 27, 2024 – Memorial Day Weekend:
  • No work to be done on Monday, May 27, 2024
  • Remove old lighting at Goodrich Park and Spring Street Parking Lots
  • Complete the Fishing Pier work in Goodrich Park
  • Install bases for new lights at Goodrich Park and Spring Street Parking Lots
  • Prepare for and potentially pave with new asphalt the parking lots at Goodrich Park, Spring Street and Shared Lot east of Mears and alley south to Spring Street