Pocket Park between Catchmark and Bell’s Furniture:
- Seatwalls have been poured
- Concrete curb and gutter has been completed
- Curb and sidewalk has been poured
- Area graded and gravel placed
- Conduit placed for new lighting
- New curb has been poured
- New storm catch basins placed
- Preparations for new lighting with new conduit
- Preparations for grading for new pavement
- New curb and sidewalk has been placed
- Preparations for grading for new pavement
- ***NOTE: We will also now be resurfacing the alley south to Spring Street with this project***
- Pilings installed
- New boulders (rip-rap) installed under the new decking
- New deck is being installed
- Waiting for old lights to be removed from Goodrich Park and Spring Street Parking Lots
- Pouring new concrete ramp and stairs to the Fishing Pier
- Finish the new deck at the Fishing Pier and Railings
- No work to be done on Monday, May 27, 2024
- Remove old lighting at Goodrich Park and Spring Street Parking Lots
- Complete the Fishing Pier work in Goodrich Park
- Install bases for new lights at Goodrich Park and Spring Street Parking Lots
- Prepare for and potentially pave with new asphalt the parking lots at Goodrich Park, Spring Street and Shared Lot east of Mears and alley south to Spring Street