Work Completed this past week (April 28 – May 2)
- Continued sanitary sewer install on 3rd Street. Roughly 600 feet from Creek.
- Continued water service install on Dewey, Main St, and 3rd St.
- Calibration of flume meter complete.
- Insert valves install on Red Bud and 3rd Street.
- Traffic to Red Bud Fitness switch to Skyline Drive. This will remain the route for traffic here until Red Bud is complete.
- Front Street Closed (Eastbound lane only) between Liberty and Rynearson for Retaining Wall repair (not part of Infrastructure project).
Work planned for this week (May 5 – 9)
- Continue sanitary sewer install on 3rd Street.
- Continue water service install on Dewey.
- Water main reconnection on 3rd Street in front of Red Bud Fitness planned for Saturday morning (5/10).