Work Completed this past week (May 19-23)
- Continued sanitary and storm sewer install on 3rd Street at City Hall.
- Traffic to Red Bud Fitness switch to Skyline Drive. This will remain the route for traffic here until Red Bud is complete.
- Water main reconnection on 3rd Street in front of Red Bud Fitness and Dewey/Main St-North completed.
- Installed vibration monitoring equipment on Front Street.
- PCMS boards updated to “Front Street Closed Starting 5-27-25”
- Front Street Closed (Eastbound lane only) between Liberty and Rynearson sfor Retaining Wall repair (not part of Infrastructure project).
Work planned for next week (May 27-31)
- Continue sanitary and storm sewer install on 3rd Street at City Hall.
- Work to begin on Front Street Tuesday, May 27th, road closure from Front Street to Oak Street will begin.
- Street Light removals beginning.
- Removals of road/curb to begin between Front and Days.