Progress Report
- Earthwork has gone as far as possible on the east side of M-52 until we can build hard walls
- Excavation continued to prepare the site for foundations to be poured for the walls on the west side
- Restoration efforts continued on the far west side
Upcoming Work Planned for Next Few Weeks:
- Foundations will be poured for the wingwalls of the tunnel
- Underdrains will be installed
- Additional preparations will be made for installing the tunnel sections in a few weeks