FRIDAY, MAY 29, 2026

  • Coopersville continues to drain/pump out its emergency storage ponds in preparation for biosolids removal and WWTP decommissioning.
  • The trenchless crossing of the 20″ HDPE force main beneath I-96 is complete. The trenchless crossing was completed via horizontal directional drill.
  • 8″ sanitary sewer stub for the East Gateway LS has been tied into the existing flood wet well at the Main LS for future connection.
  • Next week, a smaller 8″ HDPE sanitary line will be horizontal directional drilled beneath I-96. During the directional drill, the EB and WB outside lanes on I-96 will be temporarily closed.

 

Contact a Location
Learn About Us
View Our Services
Facebook-f Linkedin Youtube Instagram

© 2026 Prein&Newhof, All Rights Reserved

  • Plan Room
  • Lab Results
  • Construction Updates
  • Survey Request