Work completed/in progress:
- Completed paving HMA base course on Price Road.
- HMA top course on Price Road being placed today.
Anticipated work activities for the coming week:
- Install Pavement markings on Sherman Blvd today
- Continue HDPE force main installation of the discharge outlet piping at the lagoon.
- Continue restoration and punchlist efforts