Work completed/in progress:
- Preliminary pump installation
- Continued installation of valves, piping, and supports
- Electrical equipment and wiring
- Force main installed just short of Contract 1 force main
Anticipated work activities for the coming week:
- Grouting of pump bases and installation of motors
- Continued piping, valve, and electrical work
- Diversion Chamber concrete work