Work completed/in progress:
- Completed tree clearing activities and silt fence installation on MCRRC property and Ensley Road.
- Force main materials continue arriving on-site.
Anticipated work activities for the coming week:
- Complete tree clearing activities on Price Road and Sherman Boulevard.
- Continue receiving additional force main materials.
- Complete butt-fusion training and initial acceptance testing.
- Install dewatering system on MCRRC property north of Apple Avenue.