Work completed/in progress:

  • The first wall pour was completed this week (see photos).
  • Conduit and rebar are installed for the second wall pour.

Anticipated work activities for the coming week:

  • Forms will be stripped and moved to the next wall section. The second wall pour is scheduled for next week Wednesday.