Work completed/in progress:
- The first wall pour was completed this week (see photos).
- Conduit and rebar are installed for the second wall pour.
Anticipated work activities for the coming week:
- Forms will be stripped and moved to the next wall section. The second wall pour is scheduled for next week Wednesday.