Progress Report:

This week, Brenner has started the process of wrapping up the project by making last minute fixes to the path and finishing out with topsoiling it. M&S installed ADA ramps, and they will most likely have concrete driveways installed by the end of the day today where all concrete portions of the path will have been completed. Crosswalks have also been installed along the path this week where the final remaining crosswalk will be complete next week.

Upcoming Work:

Brenner plans on hydroseeding and completing a couple of checklist items next week. The boardwalk on Kies is nearly finished. Riverworks will continue construction, planning to wrap up once final construction materials are received.