Ric-Man has temporarily stopped pipe laying and is beginning initial restoration efforts at the southern end of the project. Pipe laying is anticipated to resume near the end of October. In the meantime, Ric-Man will continue initial restoration efforts, and begin installing pipe appurtenances (valves, air valves, hydrants) and completing work within the pipe interior.

Van Buren Street from Butternut to 160th Avenue remains closed. Pipe from Butternut to 160th Avenue has been delivered and staged along Van Buren Street.

K&R’s pipe laying has been delayed to the start of November.