Work completed/in progress:

  • Piping and valves installed and successfully leak tested
  • Gravity sewers successfully air tested
  • Driveway culvert installed
  • Conduit installation started

Anticipated work activities for the coming week:

  • Remaining conduit installation
  • Equipment pad pours