Work completed/in progress:
- Milbocker completed destructive joint sampling of HDPE butt fusion welds
- Milbocker located utilities near 68th Avenue and welded casing for the 68th Avenue crossing
- Trenchless casing contractor is de-mobilizing equipment
Anticipated work activities for the coming week:
- Butt-fusion of HDPE pipe will begin in earnest
- 68th Avenue closures is scheduled for next week. Closure is planned for one week. Here is the detour route for the closure: Detour Map
- During closure, Milbocker will install a casing beneath the road. The casing will later be stuffed with the proposed force main during winter construction.