Work completed/in progress:

  • Milbocker completed destructive joint sampling of HDPE butt fusion welds
  • Milbocker located utilities near 68th Avenue and welded casing for the 68th Avenue crossing
  • Trenchless casing contractor is de-mobilizing equipment

Anticipated work activities for the coming week:

  • Butt-fusion of HDPE pipe will begin in earnest
  • 68th Avenue closures is scheduled for next week. Closure is planned for one week. Here is the detour route for the closure: Detour Map
  • During closure, Milbocker will install a casing beneath the road. The casing will later be stuffed with the proposed force main during winter construction.