**Moorland Rd between Heights Ravenna Rd and Wilson Street is closed. This closure will last several months as force main construction continues.***
**Ellis Road is open.**
**Heights Ravenna Road will be closed starting 10/20 and will remain closed until top course of paving is complete. Follow posted detour.**
Work completed/in progress:
- Force main installation along Moorland south of Judson.
- Curb and gutter placed at Ellis Rd.
- Paved HMA base and top course on Moorland Rd from Heights Ravenna to Mt. Garfield
Anticipated work activities for the coming week:
- Continue installation of force main along Moorland Rd.
- Complete force main connection north of Crockery Creek.
- Continue crush and shape road work south of Mt. Garfield.
- Begin installation of shoulder gravel along Moorland Rd starting at Heights Ravenna.
- Close Heights Ravenna Road and begin force main installation through intersection.
- Install head walls at the ends of various storm sewer cross culverts.