**Moorland Rd between Heights Ravenna Rd and Wilson Street is closed. This closure will last several months as force main construction continues.***

**Ellis Road is open.**

**Heights Ravenna Road will be closed starting 10/20 and will remain closed until top course of paving is complete. Follow posted detour.**

Work completed/in progress:

  • Force main installation along Moorland south of Judson.
  • Curb and gutter placed at Ellis Rd.
  • Paved HMA base and top course on Moorland Rd from Heights Ravenna to Mt. Garfield

Anticipated work activities for the coming week:

  • Continue installation of force main along Moorland Rd.
  • Complete force main connection north of Crockery Creek.
  • Continue crush and shape road work south of Mt. Garfield.
  • Begin installation of shoulder gravel along Moorland Rd starting at Heights Ravenna.
  • Close Heights Ravenna Road and begin force main installation through intersection.
  • Install head walls at the ends of various storm sewer cross culverts.