Progress Report
- Oakwood Avenue: Structure adjustments have been made, and the road is prepared for final paving.
- Amsterdam Avenue: Road gravel has been installed and is being shaped and prepared for concrete curb and gutter to be installed.
- Getty Tank: All work has been completed.
- Norton: Traffic control signs were posted and notices sent to residents who will have service line replacements
- Lead Service Lines: Additional services are being replaced in the City near Waalkes, south of Broadway.
Upcoming Work Planned for the Next Few Weeks:
- Oakwood: Final paving and restoration next week
- Amsterdam: Concrete curb and gutter, sidewalks, ramps, and shaping the gravel road base for paving
- Reynolds: Final paving and restoration next week
- Norton: Between Park and Jefferson Streets, water service replacements, and a new water main in Seminole, south of Norton. The team will install new water main connections and valves at several intersections on Norton Avenue. This will be the last major project this year.
Some photos of work this week:



Please visit our dashboard for lead service line replacement to see the work that is left to be done: