Sanitary Sewer main installation has begun on Lexington Avenue and Hadden Street. Sanitary sewer installation will be completed next week on Hadden Street, with water main installation beginning in Hadden toward the end of the week.
Work Completed This Week:
- Sanitary sewer main installed on Lexington Avenue from Westwood Street to Wickham Drive.
- Sanitary sewer main installation began on Hadden Street, south of Lexington Avenue.
Anticipated Work Next Week:
- Complete sanitary sewer main on Hadden Street, north and south of Lexington Avenue.
- Begin installation of water main on Hadden Street.